Farin gida Culvert Project

StartedOct 19, 2025
CompletedNov 1, 2025
Completed
Industry, Innovation and Infrastructure
Farin gida Culvert Project

Project Overview

This project is aimed at building a culvert for the residents of the Faringida community in Kaduna State Nigeria, at Gwari road,This gulley has caused disrupted access to the road and endangered lives, especially during the rainy season for children going to school, the project will be used to mark the 50th birthday of the founder (Rev. Fr. Innocent Ojoarome Awulu CSSP) and the 2nd anniversary of the PLC humanitarian foundation, Kaduna chapter.

Target Individuals

children going to schoolVehicle owners

Sustainable Development Goals

Industry, Innovation and Infrastructure

Execution Strategy

The committee took up the challenge by writing appeal letters for financial support from individuals, faith-based organizations, and corporate bodies.

the project was flagged off on the founder's birthday i.e 19th of October 2025, the the Sarki Faringida and his council together with the CAN Faringida pastors led by the CAN chairman pastor Chucks came to the project site to inspect the items required to execute the project and pray for the success of the project

Building the culvert

the construction culvert project lasted for 5 days, from 23rd to 28th October, 2025

Day 1: Project Flagoff

location of project site
members of the CAN at the project site
The sarki of Faringida at the project site

Day 2: setting out and digging

taking measurements
workers digging the culvert

Interviews

During the construction of the culvert, the committee conducted interviews with several residents at Faringida community including the sarki of Faringida and the chairman of Motorcycle Riders Association of Faringida, to get their views on the importance of the project to the community.

Interview with the Sarki of Faringida
Interview with the Chairman of Motorcycle Riders Association of Faringida

Day 3: concrete and filling

arranging the reinforcements for the casting
casting the concrate

Day 4: Placing drainage pipes

placing the drainage pipe
casting the concrete over the drainage pipe and doing the block work for the drainage
final state

Day 5: finishing touches

 

 

 

 


Commissioning

the culvert project was successfully executed and commissioned on the 1st November 2025, and the office complex was opened on the same day, the following are some of the hhighlights of the ceremony

Arrival of guests

welcoming of guests by the founder

welcoming of guests by the founder

exchanging pleasantries

exchanging pleasantries

some of the guests seated

some of the guests seated

commencement of the ceremony

commencement of the ceremony

Welcome Address and good will messages

Founder's Address and Commissioning

Founder's Address
project commisioning by the local government chairman

Appreciation

members and volunteers of the PLC Humanitarian Foundation kaduna chapter

We give thanks to God for the successful completion of these projects. We also appreciate the Generosity of those who supported these projects in one way or another. Finally, we appreciate the support of our visionary founder and the dynamic PLC Humanitarian Team for their courage and dedication in ensuring the project’s success and keeping the needs of humanity at the forefront of all their endeavors.